2013-02-18 - 5778 - Spec - 1416 & 1420 MRP controllers creation #MRPControllers
SPECIFICATIONS
5788 - 1416, 1420 - MRP controllers creation
Purpose
1416, 1420 - MRP controllers creation
Admin Info
Purpose
|
1416, 1420 - MRP controllers creation
|
Requested By
|
Saravanan Lakshmanan
|
Spec Created By
|
Adithya
|
Spec Created Date
|
02/18/2013
|
Spec QA by
|
Adithya
|
Objects
|
T024D
|
Document Status
|
Complete
|
References
Prior Tickets
Documents
Functional Requirement
Create MRP controllers Upstairs Fall(711), Upstairs Spring(712),Upstairs Summer(713), Upstairs Holiday(714), Upstairs BCA(715), Upstairs Rhineston(716),NFL Draft (717) for the plants 1416 and 1420.
Solution Summary
[Discuss this section with Requester and get approval prior to beginning work]
As the Description was wrongly Copied due to Transport Management (One TR was deleted), Delete and recreate the MRP Controllers with the appropriate Description.
Test Plan
[List test scenarios/cases to be executed here]
|
Test Scenario
|
Expected Results
|
1
|
Create MRP Controllers 711 to 717 in plants 1416 and 1420
|
Verify MRP Controllers in Table T024D updated with exact description
|
Solution Details
[Provide complete technical details for configuration or programming here]
Delete and recreate MRP Controllers.
Issues